FloridaState Weather Alerts
There are currently no active weather alerts.

Login Status

jerib

Update on New North Causeway Bridge

From TC Palm, Earlier this year (2018)

FORT PIERCE — Construction of the new $65 million North Causeway Bridge has been delayed a year.

Work on the high-span bridge was to start in August 2020 but has been pushed back to August 2021, according to the Florida Department of Transportation. The state has had problems acquiring the property needed for the project and designing a plan that would allow access to Harbortown Marina at the western foot of the bridge.

Construction would take about 3½ years, ending in early 2025, said Donovan Pessoa, FDOT design project manager for the bridge.

Replacing the 56-year-old drawbridge is needed because it is “structurally deficient” and past its 50-year life cycle, FDOT officials said. Residents have said they want a fixed bridge instead of another drawbridge to minimize traffic delays from the bridge opening for boats traffic and traffic waiting for freight trains.

The new bridge would be built about 2,000 feet east of the existing bridge and go over Old Dixie Highway and Florida East Coast Railway tracks.  The design would extend Juanita Avenue east across U.S.1 to Old Dixie.

The new bridge would have an 86-foot clearance level, making it the tallest bridge on the Treasure Coast, allowing one sailboat with an 83-foot mast to safely clear it, according to an FDOT report on the bridge.

The height of the new bridge makes it impossible to build an exit ramp, Pessoa said. That's why the west end would take motorists past the 30-acre Harbortown Marina.

Westbound motorists exiting the bridge can turn left to enter Harbortown.

Harbortown manager Audrey Willmot said the new bridge is long overdue, but hopes it will not hurt business.

“We understand there is a need for the bridge. We see the traffic stopped when the bridge it up,” Willmot said. “But we don’t think the new bridge should make it difficult for our customers to reach us.”

The state is aware of the marina’s concern, and engineers are designing a new access road to the south of the new bridge to allow marina access from Old Dixie Highway, Pessoa said.
The new bridge would include 8-foot shoulders on each side, a 6- to 8-foot sidewalk on the south side and 10-foot shared multi-use path on the north, according to an FDOT preliminary engineering report.

The old bridge would remain until the new bridge is opened, officials said.

FDOT, Fort Pierce and St. Lucie County officials have yet to decide whether remnants of the old bridge would be left maintained as a fishing pier.

Update on Old Dixie Highway Bridge

From TC Palm, Feb 3, 2018

ST. LUCIE COUNTY — The Old Dixie Highway bridge over Taylor Creek is more badly damaged than originally believed and should be replaced, not repaired, County Engineer Kimberly Graham said Tuesday.

The bridge has been closed since Jan. 25, after an inspection showed it was not safe for travel after sustaining water damage from Hurricane Irma last year.

An engineer found the bridge's "structural integrity was questionable" and that wave action from the creek had weakened its support beams, Graham told county commissioners Tuesday.

Some areas are so deteriorated that the roadway is visible from under the bridge, she said.In some areas under the bridge, there are gaps and holes making the road on top visible.

Estimates put cost of a new bridge at $2 million repair at $400,000-$500,000. In addition to hurricane damage, it suffers from years of deferred maintenance.

"If we went ahead and repaired the bridge, it would still need to be replaced in five years," Graham said.

The commission took no action Tuesday but directed staff to work with the Florida Department of Transportation and the St. Lucie Transportation Planning Organization to find grants to pay for the replacement.

The county has applied to the Federal Emergency Management Agency for hurricane reimbursement for the damage.

"Right now, the road will remain closed indefinitely until we can find some funding sources," Graham said. "Once we have funding sources we can start the design and then have a timeline" for construction.

More than 3,000 motorists daily use the bridge as an alternative to U.S. 1. The highway connects St. Lucie County to downtown Vero Beach.

Replacement cost is part of nearly $7 million the county needs to repair more than two dozen roads damaged by Irma, according to county records.

The county is transferring about $2.2 million from capital-improvement projects to start emergency repairs for roads damaged by Irma.

St. Lucie experienced the worst of Hurricane Irma on the Treasure Coast, in terms of wind and rainfall, according to the National Weather Service.

The county received more than 21 inches of rain, almost seven inches more rain than fell in Indian River County.

Wind Mitigation Forms 2018

Wind Mitigation Forms prepared in 2018 are now available on the Tiara website.  Once you log into the website the documents can be found at www.tiaratowers.org/Support/Helpful Documents.    You can view or download the documents here.    Some insurance companies request these when your insurance coverage is issued or renewed.

 

Enjoy Memorial Day at Tiara

Holiday Greetings – Memorial Day Weekend

The Board of Directors would like to wish everyone a happy and safe Memorial Day Weekend.  Last year, the Memorial Day weekend at Tiara was a good time but there were many complaints about rule-breaking behavior on the part of owners and guests.  This behavior made many other people very uncomfortable.

A few reminders with respect to some of our rules:

  1. Overnight occupancy is limited to 6 people.
  2. All guests and visiting family members must be registered and their cars marked with Tiara parking forms.
  3. Guests of owners and tenants may not bring dogs/pets on property.
  4. No glass is allowed in the pool areas even if contained in plastic or rubber containers – all pool and spa rules should be observed.
  5. Children under 14 must be supervised by adults at all times especially in the pool areas.
  6. Shirts, Cover-ups, sandals/shoes are required at all times in the buildings
  7. No fireworks or firecrackers on property
  8. Night time gatherings on balconies should not disturb neighbors.
  9. You may reserve a party room through David in advance of the weekend.

 

Parking may be tight.  Please use approved parking in the north and south lots. (There are more spaces in the south lot than the north lot.) Do not park on both sides of the driveways leading to the building exits or the temporary parking spaces in front of each building. Parking can be done along the grass border on the east side of the A1A wall in both lots.  Emergency vehicles must have access to the property at all times.

Enjoy and have a great Memorial Day Weekend.

Summary of Board Mtg April 19 2018

Board President Bill Dicker offered this summary of the meeting held April 19, 2018.

                                             Tiara Towers Condominium Association

April 19th, 2018 Board of Directors Meeting – President’s Summary

 

Good day neighbors,

The meeting yesterday morning started with committee reports from Landscaping (7 trees have been removed – killed by IRMA and dry weather – estimates for 4 replacement trees on the way), Decorating (plans for completion of lobbies/party rooms and estimates in the Fall), Maintenance (Working on the pipe-cleaning project), Telecom (Re-cable project going well), Parking (New decals, etc have been distributed).

Old Business: The tennis court, spa, mulch, plant, tree, and door painting and rust remediation projects have been completed. New spa covers will be ordered in the late summer.  Additional lighting will be added to the pool area pergolas. Direct propane lines will connect the underground propane tanks with the grills with appropriate safety cut-offs.  Upgrades continue on the modernization of the building HVAC cooling tower infrastructure.  The purchase of new tv’s for the fitness rooms and party rooms was tabled until the May meeting. The Board accepted the donations by association members of paintings and accessories for both building entrance lobbies.

New Business:  The Association has established a relationship with a national disaster restoration company (Jarvis) recommended by our insurance Agent (Brown and Brown).  This company will be onsite immediately after a disaster with dedicated and vetted contractors to commence repairs.  New door number plaques have been ordered for all unit entrance doors. Repairs or replacement of the two lobby doors in each building are underway.  The Board will hire an engineer (to supervise and advise) and a pipe cleaning company to clean the vertical and horizontal pipes that carry waste material from the buildings to the sewer lines in the street.

 

Respectfully submitted by

Bill Dicker

 

 

 

Mix and Mingle

The Social Committee presents a Friday night "Mix and Mingle".       It's Friday April 20th at 7 pm in the North party room.    Join your friends for dessert and coffee and participate in a friendly game of "Family Feud".

No charge, just fun, All Tiara residents are welcome!

Silent Auction

The Decorating Committee is holding a silent auction Friday April 20th through Sunday April 23rd.

What:  Pictures, vases, and other objects of art that were acquired by the Decorating Committee in the past are now being made available for sale to Tiara residents*.  Pictures of these items may be found in a binder in each mailroom.

Where: All items will be displayed in the South Party Room.

When: The silent auction will start Friday, April 20th at  noon.  Final bids are due by 4 pm on Sunday, April 22nd.

Why: All proceeds will go to the Decorating Committee.

*If you have art items in excellent condition that you wish to donate to the committee, please call Nancy Mikesh. (772-465-9987)

Some of the items at the Auction are pictured below.

Palms at Ocean

Gold Mirror

Green tropical palm

 

 

 

 

 

 

 

 

There will be a minimum bid- $25 for the painted shell and green tropical palms with minimum increments of $5,    $10 for all pictures with minimum increments of $2,     and $5 for most other items with minimum increment of $1.

Painted shell

Tiara Towers Work Considered for 2018

Board President Bill Dicker offered updates on additional projects

     Tiara Towers Agenda for 2018

  1. Monitor performance of Comcast and Level 4 – Going well – Started re-cable project
  2. Monitor and manage on-going replacement of aging water heaters - DONE
  3. Continue modernization of cooling tower/HVAC infrastructure – Going well
  4. Oversee tennis court and spa renovation projects – Tennis Court done/Spa to be completed in April
  5. Oversee repair of building exterior issues: spalling and cracks – In the works ITW
  6. Prepare for painting of both buildings: bids for buildings, catwalks, railings, windows and sliders. - ITW
  7. Rust remediation & Paint remaining unit and stairwell doors – Almost DONE
  8. Plan for elevator modernization: timing, phases and financing – Planning continues
  9. Replace pool area exterior lights in both buildings – have estimates
  10. Replace pool loungers and tables – loungers OK – need two tables in each pool area
  11. Continue to explore conversion of pools and spas to salt – research continues
  12. Replace failing plants on both properties. - DONE
  13. Explore renovation or replacement of party room tables and chairs and possible re-purposing of party rooms. – Planning/Thinking continues
  14. Begin planning and investigation for replacement/re-orientation of parking lot lighting. – Plan almost done
  15. Continue to evaluate Tiara Rules, Parking, and Security needs and improvements – in progress
  16. Decorating Committee to continue with accessories and improvements for lobbies, hallways, elevator foyer, and Party rooms. – in progress
  17. Consider new tv’s in party rooms and fitness rooms. – need Board approval
  18. Introduce use of Architectural Review Committee and app forms for renovations requiring ARC review and approval. – Being used
  19. Consider making a pass/fail shutter inspection a condition of all unit sales. - DONE
  20. Arrange for cleaning of vertical soil stacks and laundry stacks plus branch mains. ESTIMATES in hand.
  21. All storage cages in both buildings were tracked to their rightful owners by a Tiara Committee and new unit numbers were placed on the cages for easy identification.

Tiara Maintenance Items for Early 2018

Board President Bill Dicker offers updates to the Maintenance Items for Tiara for early 2018

Tiara Towers Maintenance  List

  1.  Repair in front of 1203S and painting of that repair and recently repaired catwalk/rebar repairs on other floors – 1203 done – other spallings discovered – ITW – see #3 below.
  2. Resolution of leaks in 1401N, 205N and the north party room and mold remediation – Completed
  3. Repair of rebar eruptions on NE corner of north building - ESTIMATES Needed
  4. Painting of front door key/handle plates in both bldgs.  NEW Parts Ordered but not received
  5. Install of new door sweeps for ground floor doors (service entrance, garbage rooms, generator rooms, FPL rooms) in both bldgs. DONE
  6. Five new lanterns in the crossover between both buildings -DONE
  7. Mulch all planting areas - DONE
  8. New plantings where needed on both lots - DONE
  9. New control system for HVAC systems in both bldgs. – Ready for install plus new pumps and motors. 30 Valves to be replaced.
  10. Paint six pool gates – IGNORED so far
  11. Re-marcite both spas - APRIL - In Progress at this time
  12. Re-build tennis court – DONE
  13. Re-install “T” blown off front gate by hurricane - DONE
  14. Estimate to paint unit and stairwell doors – DONE
  15. Pool level device in north pool - DONE
  16. Estimates for painting both bldgs.. – Have one, awaiting 2 more for Summer 2019
  17. Repair of North Bldg. beach walk – SCHEDULED FOR SUMMER Sat work by David
  18. Paint inside of hobby room doors in both bldgs. -SCHEDULED
  19. Complete decorating project in north bldg. DONE
  20. Deal with rust on some of the garage and garageport doors in both bldgs.. – WAITING for ESTIMATES
  21. Install new light fixtures on GARAGE AND GARAGEPORT exteriors – DONE
  22. Order new spa covers – Have estimates will order in the fall
  23. Clean interior of soil stacks, branch mains and possibly the laundry stacks. Have estimates from 3 companies – Late Spring/Summer
  24. Cut down 8 trees killed by IRMA. – DONE
  25. North border hedge with the vacant lot dying. - Investigate
  26. Begin retrofit of catwalk lighting for LED bulbs - ITWs
  27. New heater for North bldg.. spa – DONE
  28. Estimates from Decorating Committee for drapes, additional accessories, and re-upholstery of community room furniture. – Being developed
  29. Paint parking area curbing – SUMMER work
  30. COMCAST re-cable project – Started 2d week of April
  31. Buy and install new unit door number plaques.
  32. Replacement of 9 unit and stairwell doors.

Update on Comcast Re-Cabling

The Comcast technicians began the re-cabling work on April 9th, starting in the North tower.     There will be an estimated schedule by date and floor, posted in the elevators, for the continuing days and weeks to assist owners in figuring out when their unit might be re-cabled.   The work began in the North tower, on the 15th floor, will work its way down and then move to the South tower.   Preliminary estimate is “one floor per day” and if that turns out to be accurate then it’ll take 6 weeks to complete the project.

During the coming week (April 16-20) the technicians will be working on floors 10 thru 6 in the North tower.   Watch the elevator for weekly updates.

For those owners who said they would Hide the cabling, rather than use the wire mold, here is a list of contractors you can contact to do the work in your unit.

Rick @ Doc Drywall   (772) 828-5956

Doug’s Drywall (772) 646-3112

Alan Whiteside Drywall (772) 539-1955

Bill Normington  (916) 759-6970

Bob Alexander (903 S) is managing the re-cabling effort and doing a great job.   Please call Bob if you have questions about the schedule in general or your unit in particular or if you’d like his help in coordinating the drywall work for your unit.